Requirements for qualification of manufacture of the ITER Central Solenoid and Correction Coils
Ist Teil von
Fusion engineering and design, 2015-10, Vol.98-99, p.1103-1108
Ort / Verlag
Elsevier B.V
Erscheinungsjahr
2015
Quelle
Alma/SFX Local Collection
Beschreibungen/Notizen
•A manufacturing line is installed for the ITER Correction Coils.•A manufacturing line is under installation for the ITER Central Solenoid.•Qualification of the manufacturing procedures has started for both manufacturing lines and acceptance criteria set.•Winding procedure of Correction Coils is qualified.
The manufacturing line of the ITER Correction Coils (CC) at ASIPP in Hefei (China) was completed in 2013 and the manufacturing line of the ITER Central Solenoid (CS) modules is under installation at General Atomic premises in Poway (USA). In both cases, before starting production of the first coils, qualification of the manufacturing procedures is achieved by the construction of a set of mock-ups and prototypes to demonstrate that design requirements defined by the ITER Organization are effectively met. For each qualification item, the corresponding mock-ups are presented with the tests to be performed and the related acceptance criteria. The first qualification results are discussed.